RCC and Waeger Constructions’s Precast Column Install Commenced at St Bede’s Catholic College

This 22T, 12m high column is one of the biggest construction innovations helping build the St Bede’s Catholic College Chisholm.

Precast column are transported horizontally on trucks to site and rotated into their final vertical position. Source: Richard Crookes Constructions

RCC and Waeger Constructions’s bespoke precast column solution on the project involves sky high structural and architectural feature columns, being transported horizontally on trucks to site and rotated into their final vertical position.

Each precast column weighs approximately 22 tonnes, measuring in size from 1650 long x 500 wide and ranging in height from 7m-12m, without the need for any temporary propping. The columns which extend the full height to the underside of the roof and feature a tapered profile, externally visible around the perimeter of the building.

Precast column install. Source: Richard Crookes Constructions

Pouring these columns insitu (on site) would have presented challenges in relation to materials, plant and labour requirements, so this precast column enhances project efficiency, quality and safety outcomes.

Increased quality control and the ability to form full length columns as well as adjustments to people and plant movements and delivery across multiple work fronts enhances RCC’s programme and safety management on site.

Precast column install commenced at St Bede’s Catholic College. Source: Richard Crookes Construction

Source: Richard Crookes Constructions